TxDOT to Begin Implementing Final I-35 Traffic Shifts Feb. 28-March 4

February 21, 2022
Final Traffic

TxDOT will begin implementing the final traffic shifts on I-35 as crews work to complete construction by early 2023. The diagram shows final traffic shift phases.

WACO, Texas (Feb. 21, 2022) – The Texas Department of Transportation (TxDOT) has rescheduled the northbound I-35 mainlane traffic shift from US 84/Waco Drive to N Loop 340 due to expected weather events this week. These are among the final traffic shifts for the I-35 project through Waco, which is anticipated being completed by early 2023.

WHAT YOU NEED TO KNOW:

Two traffic shifts are planned to move all northbound traffic to the newly reconstructed northbound mainlanes. The first shift will be north of the Baylor campus from US 84/Waco Drive to N Loop 340.

Monday, Feb. 28, to Friday, March 4, from 7 p.m. to 6 a.m.

  • To prepare for the first shift, TxDOT plans to close alternating northbound mainlanes north of campus from N Loop 340 to Craven Avenue and the northbound I-35 entrance ramp near N Loop 340 nightly Monday, Feb. 28, to Friday, March 4, from 7 p.m. to 6 a.m.

Monday, Feb. 28, to Friday, March 4, from 5 p.m. to 6 a.m.

  • Crews also plan to close the northbound exit ramp to N Loop 340 (Exit 339) nightly Monday, Feb. 28, to Friday, March 4, from 5 p.m. to 6 a.m. These closures will allow crews to move barriers, stripe and shift traffic onto the newly reconstructed lanes.

All northbound traffic from US 84/Waco Drive to N Loop 340 is expected to be shifted with ramps open by Friday morning. Traffic will remain two lanes in each direction as crews complete work on the inside north and southbound I-35 mainlanes.

Schedules are dependent on weather, field conditions and work progress. Plan ahead and visit waco4bmap.org for real-time traffic and pedestrian crossing information on I-35 through Waco. Follow @TxDOTWaco on Twitter for the most current updates on construction activities and lane closures.